BOLT and BOT schemes
Infrastructure is the word used to collectively refer to the facilities like roads, railways, bridges, manufacturing plants etc. A good infrastructure is a prerequisite for economic growth. The infrastructure development was taken up on a large scale during the last decade. The Government envisaged the nation wide infrastructure development through the participation of the private sector. The investment required for these projects were huge and the gestation period of these projects were also quite high. The Government with a view to encourage the private participation in these developmental projects offered various business, models like BOOT, BOLT & BOT.
BOLT
It is a non-traditional procurement method of project financing whereby a private or public sector client gives a concession to a private entity to build a facility (and possibly design it as well), own the facility, lease the facility to the client, then at the end of the lease period transfer the ownership of the facility to the client.
As a system of project financing this procurement method has a number of advantages the major one being that the private entity, contracted by the client, has the responsibility to raise the project finance during the construction period. What this does is to remove the burden of raising the finances for the project from the client (i.e. the public enterprise) and places it on the private entity. This way the BOLT developer assumes all the risk, the risk of raising the project financing and the risk during the construction period. Of course such risk is not undertaken for free by the developer but comes at a cost, which is passed onto the client. The operational and maintenance responsibility for the facility is the developer’s, as the facility is owned by them until the lease period ends.
The lease period will see the client who in essence becomes the tenant of the facility, paying the developer a lease (monthly or annually) for the use of the facility at a predetermined rate for a fixed period of time. The lease payment becomes the method of repaying the investment, and ultimately rewarding the developer’s shareholders. At the end of the lease period, ownership of and the responsibility for the facility are transferred to the client from the developer at a previously agreed price.
BOT model
A build-operate-transfer (BOT) contract is a model used to finance large projects, typically infrastructure projects developed through public-private partnerships.
The BOT scheme refers to the initial concession by a public entity such as a local government to a private firm to both build and operate the project in question. After a set time frame, typically two or three decades, control over the project is returned to the public entity.
Under a build-operate-transfer (BOT) contract, an entity—usually a government—grants a concession to a private company to finance, build and operate a project. The company operates the project for a period of time (perhaps 20 or 30 years) with the goal of recouping its investment, then transfers control of the project to the government.
BOT projects are normally large-scale, greenfield infrastructure projects that would otherwise be financed, built and operated solely by the government. Examples include a highway in India, a wastewater treatment facility in China and a power plant in the Philippines.
In general, BOT contractors are special-purpose companies formed specifically for a given project. During the project period—when the contractor is operating the project it has built—revenues usually come from a single source, an offtake purchaser. This may be a government or state-owned enterprise.
Power purchase agreements, in which a government utility acts as offtaker and purchases electricity from a privately owned plant, are an example of this arrangement. Under a traditional concession, the company would sell to directly to consumers without a government intermediary. BOT agreements often stipulate minimum prices the offtaker must pay.
A number of variations on the basic BOT model exist. Under build-own-operate-transfer (BOOT) contracts, the contractor owns the project during the project period. Under build-lease-transfer (BLT) contracts, the government leases the project form the contractor during the project period and takes charge of the operation. Other variations have the contractor design as well as build the project. One example is a design-build-operate-transfer (DBOT) contract.
APSC Notes brings Prelims and Mains programs for APSC Prelims and APSC Mains Exam preparation. Various Programs initiated by APSC Notes are as follows:-- APSC Mains 2024 Tests and Notes Program
- APSC Prelims Exam 2020- Test Series and Notes Program
- Apsc Prelims and Mains 2024 Tests Series and Notes Program
- Apsc Detailed Complete Prelims Notes